Schedule as of January 23, 2019

Phase Date
Architect Selection August 2018 - September 2018
Schematic Design (SD)/ Occupant Group Design Review September 2018 - December 2018
Permitting December 2018 - June 2019
SD Estimate & Approvals December 2018 - March 2019
Design Development/Occupant Group Design Review January 2019 - June 2019
Site Preparation April 2019 - June 2019
Construction June 2019 - April 2021
Building Occupancy Summer 2021

On-going construction of Green-line Extension is being closely coordinated with the MBTA - planned opening in 2021.